Ongoing Electrification Works of South Eastern Railway

Ongoing Electrification Works of South Eastern Railway

SER GOING AHEAD WITH ELECTRIFICATION WORK IN ALL SECTIONS TO CURB POLLUTION AND TO REDUCE JOURNEY TIME

Railway Electrification has played an important role in the country by providing the most energy efficient, pollution free and speedy mode of transport to the nation. In South Eastern Railway, total 88% (percent) of the entire route kilometre has already been electrified which includes the main and trunk route. For the rest portion, South Eastern Railway has taken major initiatives to complete the electrification works in the branch line sections.

The ongoing electrification works of S E Railway are in rapid progress. The Bankura-Sonamukhi (41 KM), the part of Bankura-Masagram electrification project (118 KM) having a total estimated cost of 106.45 crores is in completion stage.

Electrification of Tatanagar-Badampahar section (89 KM) having an estimated cost of Rs. 105.42 crore is in rapid progress and expected to be completed within schedule time.

The electrification work of Rupsa-Bangriposi (89 KM) is going on full swing with an estimated cost of Rs.94.89 crores and is expected to be completed within stipulated period up to Baripada in first phase.

Completion of the above projects will help South Eastern Railway to operate seamless movement of train service without any change of traction and will lead to the reduction of journey time of the passenger carrying trains.

Leave a Reply

Your email address will not be published. Required fields are marked *

error: